Update on Clubhouse Renovations

Update on Clubhouse Renovations

UPDATE by The Wildewood Club on March 26, 2022

The Wildewood Club Downstairs Remodel Status Report.

Work on the Downstairs Remodel has steadily moved forward since the last message posted after receiving the Permit to Construct from Richland County. Over the past week, the new floor drains were inspected and approved for concrete pouring to cover the saw cuts. Plumbing rough in continues for the new locker room fixtures. All the new walls have been stood up. You can now appreciate the spatial aspect of the new floor plan.

Our electrical contractor has completed the new wiring installation in the Pro Shop area. On Thursday the Richland County inspector completed a detailed inspection of the installation and approved the work in the Pro Shop area. On Friday 03/25/2022 the sheet rock installers began installing sheet rock in the Pro Shop.

Other activities this past week include the installation of Low Voltage wiring to support Ethernet and coaxial cable and mechanical installation of duct work. Locations of the Lockers was finalized. Key commodities such as doors, windows and lighting continue to be tracked. Interior design decisions such as flooring selection, paint colors and furnishings are being followed up on as well.

In summary, there are still many moving parts our team is tracking to meet the target dates:

  1. Be back in the new Pro-Shop by April 15th
  2. Open the new locker rooms by May 23th
  3. Open the Grill by May 30th

The Richland County Demolition permit was issued on January 25,2022 allowing the project to move forward and the Permit to construct was issued on March 10,2022.

We thank you for your patience and working through several inconveniences during construction. We have assured our Contractor there will be no punishment for and early finish. All parties are committed and working hard toward the key millstones.

The Wildewood Construction Team